The Waubra Wind Farm Project is located in Waubra, approximately 35kms North West of Ballarat and is the largest renewable power project in the Southern Hemisphere. The Wind Farm is situated in two municipalities, the Shire of Pyrenees and the City of Ballarat. The project site (approximately 173km²) is a series of hills and high plateaus which form part of the Great Dividing Range. The site consists primarily of cleared agricultural land used for sheep and cattle grazing and potato growing.
The Waubra Wind Farm began generating sustainable, green power in February 2009 and will be fully operational from the end of June 2009.

Waubra Wind Farm locality map. A detailed site layout map can be viewed here
The Waubra Wind Farm will comprise 128 wind turbines, associated access tracks, substations and a Maintenance Facility. Each turbine will generate 1.5 megawatts (MW), providing a total installed capacity of 192MW. The green energy generated by the Wind Farm each year will deliver approximately 650,000 tonnes of CO2 savings. At peak, the Wind Farm will generate enough green energy to power more than 140,000 homes or enough electricity for the City of Ballarat and surrounding areas. The Waubra Wind Farm will help Victoria to meet it's future energy needs without further contributing to the cause of climate change.
The construction of the Waubra Wind Farm Project has been made possible by the Victorian State Government’s commitment to a Victorian Renewable Energy Target (VRET). The VRET provides regulatory stability for investments in clean energies by requiring that electricity retailers purchase a minimum 10 per cent renewable energy by 2016. This scheme fosters the sale of energy produced from wind farms.
ACCIONA Energy engaged in significant consultation with the local community on the Wind Farm design. Detailed information on the design was presented to the Community Reference Group (CRG) and at a Community Information Day. The completed, detailed design includes the electrical design, the selection of turbines that best fit the terrain at Waubra, a lighting plan for aviation safety and the design of a sustainable, maintenance building. ACCIONA Energy continues to keep the community informed and engaged through several methods including quaterly meetings with the CRG, Newsletters and Project Updates.
The design of the electrical system consists of mostly underground cabling, some overhead lines, five substations and a terminal substation. All electrical cables between turbines are installed underground to reduce the amount of overhead lines required.
The Waubra Wind Farm site is a combination of hills and flat plains. Wind turbines have been selected to match the particular wind conditions and the local terrain at Waubra. The detailed design includes three turbine configurations; all are based on the same ACCIONA Windpower 1.5 megawatt model, but with a combination of tower heights and blade lengths. Tower heights and blade lengths range from 110 and 120 metres.

As just over half of the turbines in the Wind Farm will have a maximum blade tip height above 110m, the Civil Aviation Safety Authority (CASA) recommended installing aviation safety lighting. Lights will eventually be installed on 48 of the 128 wind turbines to ensure the Wind Farm is visible to aircraft pilots in hours of darkness.
Above: Facility Manager, Glenn Wright at the Waubra Wind Farm Maintenance Facility.
The ACCIONA Energy, Waubra Wind Farm Maintenance Facility showcases environmentally sustainable design and visually complements the surrounding environment. The low energy building is constructed from sustainable materials and will be powered with 100% wind energy.
The construction of the Maintenance Facility was awarded to the regional company AW Nicholson. Construction was completed in October 2008. Final touches are currently underway for an indigenous garden and outside walk ways.
The Maintenance Facility caters for 26 permanent on-site staff and up to 200 contractors who are currently undertaking the construction and commissioning of the Wind Farm before it becomes fully operational. The 880 m² Facility is used for all maintenance activities and also provides storage space for equipment, vehicles and spare parts.
The civil construction works are complete for all 128 wind turbines. Turbine installation commenced in December 2007. ACCIONA Windpower, ACCIONA Energy’s sister company, is supplying the turbine parts and managing the construction and commissioning of the wind turbines.
The towers are being produced by Keppel Prince Engineering, a local Portland company, and by Haywards Engineering in Tasmania. The nacelles and hubs are being manufactured by Acciona Windpower in Pamplona, Spain, and the blades by Tecsis in Brazil.
ACCIONA Energy is currently undertaking energisation and commissioning. All wind turbines need to be tested before they start operating to produce electricity. The first turbines began generating green power in February 2009 and the entire site will be fully operational from the end of June 2009.
Electrical works commenced in January 2008. Downer EDI Engineering was the lead contractor for the electrical works including laying underground cables, constructing 66KV overhead lines and building the five substations. Victorian company Powercor Electrical Services has been subcontracted to construct the overhead lines. Electrical works will be completed by early 2009, weather permitting.
The Waubra Wind Farm is a significant investment in the region and is having a positive effect on the regional economy. Past Premier, Steve Bracks, and Minister for Energy Industries and Resources, Theo Theophanous, said the project would provide more jobs and economic activity for the region (click here to see their media release dated 18 July 2006).
The Wind Farm will also provide additional income for local landowners involved in the project and is also expected to bring tourism and the associated benefits to the area.
ACCIONA Energy is committed to using local construction and manufacturing skills and to sourcing local equipment and materials wherever possible. Aproximately 26 permanent jobs have been created for the ongoing operation and maintenance of the Wind Farm. At the peak of the construction phase, the Wind Farm had created around 200 jobs.
To date more than 20 regional businesses have been involved as subcontractors, such as Eureka Concrete from Ballarat. (More than $200 million worth of supply, building and construction contracts have also been awarded by ACCIONA to local Australian companies for the Waubra Wind Farm, predominantly in Victoria; a further $2B worth of projects have been approved for construction in NSW, Victoria and South Australia.)
ACCIONA Energy has established a sponsorship program to support the local Waubra community during the construction phase, which has provided financial and in-kind sponsorships. ACCIONA Energy has supported community groups including the Waubra Football and Netball Club; the Waubra Kindergarten’s refurbishment of its playground; the Lions Club upgrade of the Family BBQ area at Toll Bar Park in Lexton; and has provided ‘sustainable raffle prizes’ for community groups fund raising activities. The Company has also supported the local CFA with water trucks being made available to fight fires.
A Sustainable Community Fund has been established to share the benefits of the Wind Farm widely and to support local projects. Once the Wind Farm is operational The Community Fund will provide approximately $64,000 per year (indexed to CPI) and will contribute over $1.6 million to the local community over the life of the project.
ACCIONA Energy is committed to helping the Waubra Wind Farm community achieve their goals through support from the Sustainable Community Fund. Planning is currently underway to manage the administration of the Sustainable Community Fund.
Above: Terminal station at Waubra Wind Farm
Wind Farm Construction Manager, Bruce Payne and Captain of Waubra Football Seniors Team, Shaun Mullane: both have worn no. 7 and both work at the Waubra Wind Farm site.
Parents and children of the Waubra Kindergarten and
ACCIONA Energy staff in the playground.